WORKS AND ENGINEERING
WORKS AND ENGINEERING
The Works and Engineering Department is headed by the City Engineer and is responsible for providing technical support and guidance on the urban structural design, infrastructure improvement, road network development and maintenance and control of infrastructure developments in the City.
During the implementation of LGDPII, Lira City has had a total of about 37 kilometers of paved roads, 183kms of Gravel and 66kms of Earth road roads. This implies that, the Proportion of paved roads to total roads is 15%, unpaved road network in fair to good condition is 35%, while paved road network in fair to good condition is at 19.5%.These roads are in motorable states and has led to reduction in roads traffic accidents.
Lira City has six Major roads that cut through and go to other Cities. These are Lira Kampala road, Lira Aloi road, Lira Apac road and Lira Boroboro road Lira –Soroti, and Lira –Kitgum Road. Besides the major roads, there are also many minor roads within the City such as Adekokwok road, Erute road among others and very many Local roads which provide access to different villages and areas. Some of these roads have been opened up recently in the respective divisions. The most common means of transport is private with 74% being use of private transport. Bicycles are the common mode of privet transport with 64% owning Bicycle, and 12.2% owning Cars.
WORKS DEPARTMENTAL REPORT
Work and Engineering is mandated to:
Plan, design, implement, maintain public infrastructure in the City
Control private physical development in the City
Regulate and ensure compliance to the construction practices
Advise the entities on appropriate method, system, material for physical development
Inspects plants, equipment, machine, tool, buildings, roads, bridges, drainage, structures, open space, boundary walls, excavation etc. and recommend them for public use
EQUIPMENT AVALIABLE
i Motor Grader Grounded
ii Tractor it is in a very poor mechanical condition
iii Pedestrian roller it is old and frequently break down
iv pick up truck it is old and frequently breaks down
IMPLEMENTED ACTIVITIES FOR FY 2023/24 UNDER TRANSPORT REHABILITATION GRAND
In FY 2023/2024 the IPF for Transport Rehabilitation grand was shs 1000,000,000 and we have received all the fund. the following activities were planned
Road Rehabilitation on 14 roads with a total length of 35km at Shs 859,086,900=
Road inventory and condition surveys Shs 24,00,000=
Mechanical impress Shs 40,000,000=
Administration cost Shs 54,000,000=
Environmental Mitigation Shs 10,000,000=
THE FOLLOWING ARE THEROADS WORKED ON
S/N PROJECT NAME SCOPE OF WORK REMARKS
1 Te-Ebira (1.8km) Bush clearing, Scarifying, gravelling and drainage works completed
2.Te-Okole(5.5km) Bush clearing, scarifying, gravelling and drainage works completed
3.Okot Ongon Bottle Neck culvert installation completed
4. Okello Oula RD (0.8) Bush clearing, scarifying, gravelling and drainage works on going
5. DOC -Agoni Rd (3km) Bush clearing, scarifying, gravelling and drainage works on going
6. Onapa road (1.2km) Bush clearing, scarifying, gravelling and drainage works on going
7.Okori olero (ikm) Bush clearing, scarifying, gravelling and drainage works on going
8. Ogwang john Rd(2.4km) Bush clearing, scarifying, gravelling and drainage works completed
9. kole Rd (1KM) Bush clearing, scarifying, gravelling and drainage works On going
10. Adekokwok aiia (12km) Bush clearing, scarifying, gravelling and drainage works On going
11.Te-mogo (1.2KM) Bush clearing, scarifying, gravelling and drainage works completed
12,Kulu Owelo Bottle Neck Bush clearing, scarifying, gravelling and drainage works On going
13. Anai Agali Bypass( 6KM) Bush clearing, scarifying, gravelling and drainage works on going
14. Cuk- Ebange road (0.3km) Bush clearing, scarifying, gravelling and drainage works on going
IMPLEMENTED ACTIVITIES FOR FY 2023/24 UGANDA ROAD FUND
In FY 2023/24 the IPF for Uganda Road Fund was shs 309,716,000 and we received all the fund .the following activities were planned;
Routine Manual Maintenance (Gangs work) shs 101,016,00=
Routine Mechanized Maintenance (2.4km) at shs 77,000,000=
Mechanical Impress shs 8,000,000=
Environmental Mitigation 5,000,000=
Purchases of tool and safety wear shs 40,000,000=
S/N PROJECT NAME SCOPE OF WORK
1 Bar-apwo to Bala boarder Bush clearing, grading, spot gravelling and drainage works
2 Aler Compost Access Road Bush clearing, grading, spot gravelling and drainage works
3. Aputi road patching
PROJECTS UNDER USMID
1 Beautification of mayor garden
2. supply of street lights
3 Repair of 150 solar lights
4 Beautification of Tipper Stage
5 Roads and parks
CHALLENGES IN THE IMPLEMENTATION OF URF
URF guideline recommends that all the activities must be executed under force account mechanism ,below are the challenges affecting the performance;
Lack of road equipment to implement the works, Lira City Council has only one motor grader, which is grounded and there is no any other Equipment, we opted to Hired of road Equipment which affected our initial planning
Late releases of the funds
Delay in the procurement processes for the materials to be used on the road
inadequate staff leading to too much worked load on the few existing staffs
Non -payment to the service provider leading low supply fuel
- Plan, design and manage the construction, rehabilitation, upgrading and periodic maintenance of the City Roads including the Road marking and signage.
- Plan, design and manage the construction, rehabilitation and maintenance of the City drainage systems.
- Plan, design and manage the provision of traffic, manage street parking space and street lighting for the City.
- Plan, design and manage public transportation in the City and monitor and propose areas for improvement of City traffic.
- Plan, design and manage the construction and maintenance of the City building infrastructure
- Provide technical guidance on the contractual issues relating to bills of quantities provided in relation to materials supplied for construction projects.
- Contract professional firms to revamp the City infrastructure, road network, for a modern and easy accessible City.
- Develop and monitor the implementation of road walkways, fly overs, traffic signal junctions, major interchanges and bridges construction, and maintenance policies and procedures as per the City Mandate.
- Develop, review and update the Wider City Transport Master-plan.
- Develop and implement road safety strategies for reducing road causalities within the City.
- Compile and analyze transport and road safety data and prepare reports.
- Building Permits.
- Occupation Permits.
- Roads maintenance.
- Road Opening.